ASME BPV-III-1-ND, AutoPIPE Nuclear Piping Code Calculation Issues in AutoPIPE


Boiler & Pressure Vessel Code, Rules for Construction of
Nuclear Power Plant Components Division 1,
Subsection ND, Class 3 Components

Note: Please see the following AutoPIPE help section: 

Help > Contents> Contents Tab> Reference Information> Code Compliance Calculations> select a piping code to see the calculations performed by AutoPIPE.


Comments, Questions, and Answers on ASME ND Piping code in AutoPIPE

  1. Service Level C coincident pressure P differs from the Peak Pressure (Level A and B), specified which to used
  2. Find SIF use for stress calculations at each point
  3. Zero moment and its involvement in ASME ND eq. 10
  4. Non-repeated Anchor Movement (e.g. Building Settlement) eq.10a
  5. Building settlement
  6. Calculated allowable for "ASME ND (2007) PRE-VERIFICATION STRESS REPORT", Eq 8, Load case = GR
  7. Valve and Flange end connections availability between ASME NB - NC - ND
  8. Pre-verification report does not show if range moments (amb T1, amb T2…T1 toT2 …)
  9. ASME ND Sustained category combinations and pressure load
  10. Use of HDPE cold allowable
  11. Satisfy NB-3653.1 through NB-3653.6, using stress Summary A and B
  12. High CUF values caused by Forces / Moments having opposite signs about a Tee node point
  13. Results are given for Equations 10 and 11 (and 12 and 13 if 10 is non-compliant)
  14. Stress summary Eq.9 appears to be ranging
  15. Equations missing from output report