Slope stability for road construction project: using FEM and LEM [PLAXIS LE]


Application PLAXIS 2D
PLAXIS 2D LE
Version PLAXIS 2D CONNECT Edition V21.01
PLAXIS LE CONNECT Edition V21
Status Technology Preview
Date created 11 May 2021
Date modified 11 May 2021

Introduction

On the North Island of New Zealand a new road section has to be constructed along the shore line of a tidal bay, see figure 1.

Figure 1: Situation overview for the newly constructed road

Though the easiest solution would have been to construct the road at a larger distance from the bay as the slope gradients are easier there, this is not possible as the upper land is privately owned which for historic reasons cannot be changed. The new road therefore had to be constructed along the steeper gradient just next to the shoreline of the tidal bay.

The hillside is mainly siltstone, weathered at the surface but intact at certain depth. Construction will take place in summer when the ground water level is low. However, in winter the hillside side almost fully saturates due to heavy rainfall, which has a significant influence on the stability. For the construction of the new road part of the slope was excavated. The excavated material is crushed and mixed with sand and gravel to make fill material to support the road.

During the first winter after the road construction the road started to tilt towards the tidal bay and after assessing the winter situation the factor of safety was considered too low. The decision was taken to stabilize the fill and hillside below the road using so-called launched soil nails: long steel reinforcement bars that are shot with high speed into the ground.

 

Additionally, concerns have raised about rock fall and landslides above the road and thus an additional analysis of the slope stability above the road must be performed. The strength reduction method in Finite Elements gives the most critical slip surface, but it's not so easy to determine a factor of safety for a specific area and therefore for the slope stability above the road a Limit Equilibrium analysis is used.

Main goals

Main goal of the analysis:

Requirements

To run this tutorial case, you will need the following:

Downloads

See also