AutoPLANT some component has schedule and some component has rating. While generating isometric user may have requirement to show rating and schedule under one column.
Following illustrative steps will help you to get schedule and rating under one column in bill of material.
Note: For an AutoPLANT user, the report.def file can be open by navigating to project path under style>config Folder,
C:\ProgramData\Bentley\Plant V8i\Bentley Plant V8i Projects\SAMPLE_METRIC\Config\OpenPlant \Isometrics \styles\IFC\config\report.def
4. Edit report.def file add following entries
COLUMN = 10: L : SCHEDULE + “ “ + RATING
5. Save ‘report.def’ file.
6. Generate isometric to review the result.