Resources represent People, Equipment, and Other Materials used on a project. SYNCHRO Perform manages these Resources by assigning them to projects, and setting rates for cost analysis.
The purposes and capabilities of each Resource type are:
Resource
|
Purpose
|
Unique in SYNCHRO Perform?
|
Assignable to multiple SYNCHRO Perform Projects?
|
Can have time varying Rates and Roles?
|
Can capture Time & Usage?
|
Can capture Attendance?
|
Can be used for Telematic Tracking?
|
People
|
Real (named) people
|
Yes
|
Yes
|
Yes
|
Yes
|
Yes
|
No
|
Equipment
|
Physical (named) plant and equipment
|
No
|
No
|
Yes
|
Yes
|
No
|
Yes
|
Other
|
Any other resource types (materials, generic people and equipment)
|
No
|
No
|
Yes
|
Yes
|
No
|
No
|
People are unique in an SYNCHRO Perform instance, and can be assigned different rates and role across projects. This ensures that duplicating (or re-creating) a Person if they move projects, or start a new project, is not required. However, Equipment and Other Resource types are specific to each project, and cannot be assigned to multiple projects.
Assigning a Resource to a project is called a ‘Resource Assignment’, and is used for People, Equipment and Other Resource types. These allow Resources to be assigned to different companies and roles over time. However, a resource can only have one Resource Assignment at any one time. To support reporting, historic (or prior) Resource Assignments are stored in SYNCHRO Perform.
Create Resources - People
- To add People, select Resources > People.

- First, ensure a Person has not been added already by searching the Person’s name in the Search box.
- Select Current, Previous, and Never before searching to ensure no entries are missed.
- Add people by clicking Add Person, and add work roles with Add Work Role; Work Roles should be added before being used for a Person.
- Enter details in the page that opens as needed, ensuring all boxes marked with an asterisk are filled.
- Selecting a Roster Work Code automatically populates the Work Roster.
- Selecting a Supervisor automatically populates the Supervision Roster.
- Employment details can also be added as needed.
- If a Person is a Supervisor, click the Supervisor? checkbox (required), and assign a Supervisor Code as needed*.
A unique code, up to 5 capital letters and/or numbers. - When all information is entered, click either Create Person or Create Work Role.
Each person’s name must be unique; if two people share a name, add an additional initial.
* The Supervisor Code assists in filtering, identifying, and rostering, and can also be used to identify a Supervisor when entering Usage
Create Resources - Equipment
- To add Equipment, select Resources > Equipment.

- First, ensure the Equipment has not been added already by searching the Equipment’s name in the Search box.
- Select Current, Previous, and Never before searching to ensure no entries are missed.
- Add equipment by clicking Add Equipment Item, and add equipment types with Add Equipment Type.
- Enter details in the page that opens as needed, ensuring all boxes marked with an asterisk are filled.
- When all information is entered, click on either Create Equipment Item or Create Equipment Type.
Create Resources - Other
- To add other materials, select Resources > Other.

- First, search the Other Resource’s name in the Search box to ensure it has not already been added.
- Select Current, Previous, and Never before searching to ensure no entries are missed.
- Add materials by clicking Add Other Resource, and add material types with Add Other Resource Type.
- Enter details in the page that opens as needed, ensuring all boxes marked with an asterisk are filled.
- When all information is entered, click on either Create Other Resource or Create Other Resource Type.
Assign Resources
Resource Assignments define the Company, Work Role/Type and the period the assignment spans.
Only one Resource Assignment per Project can be active at any one time.
- To assign a Resource, navigate to either People, Equipment, or Other, then click on an item.

- The item’s page shows all assignments for a Resource; for a new assignment, select a project from the dropdown menu, then click New Resource Assignment.
Note: A single Resource can have different roles in different projects, however it cannot have two
roles in the same project. - Enter details in the page that opens as needed, ensuring all boxes marked with an asterisk are filled.
- When all information is entered, click on Create Resource Assignment.
- Alternatively, to edit an existing assignment, click on the
icon on the item’s page, make changes as needed, then click Update Resource Assignment.