Work Inspector - Schedule


The Work Inspector tracks an Activity’s schedule dates, such as Planned Start and Finish, and can also update and edit these attributes.

  1. Click on Activities > Work Inspector > Schedule.

    An Activity’s various start and end dates can be set from this page.
  2. If a cell has no date, click Start, Set, or Finish as needed, then select a date.
    If a cell is blank, or coloured red, another start or end date for the Activity must be updated before it can be edited.
  3. Hover over the cell for information on which cell must be updated.