The Work Inspector tracks an Activity’s schedule dates, such as Planned Start and Finish, and can also update and edit these attributes.
- Click on Activities > Work Inspector > Schedule.

An Activity’s various start and end dates can be set from this page. - If a cell has no date, click Start, Set, or Finish as needed, then select a date.
If a cell is blank, or coloured red, another start or end date for the Activity must be updated before it can be edited. - Hover over the cell for information on which cell must be updated.
- To edit an existing date, click on the
icon, then select a new date.