Labour and Plant Dockets are intended for use by individual subcontract workers submitting hours worked and work completed for a Person and up to three Equipment items, using multiple units of measure as needed.
- Select Dockets > Labour & Plant Docket.

- If a single Docket is needed, (consult the Site Champion to clarify), click Yes on ‘Record to single Docket?’.
- Click either Scan or Search by Name to enter a Person’s details.
- If Scan, use the device to scan their QR code.
- If Search by Name, enter their details and select the check box next to their name.
- Enter a Start Time, End Time, and Break Duration as needed.
- To add Equipment, click Yes on Add Equipment Item as needed.
- To search for equipment and enter times, follow the same process for adding a Person.
- Click Set on ‘Equipment SMU Start/Finish’ and enter measurements as needed.
- To add additional Equipment, click Yes on ‘Add Equipment Item’ as needed.
- Search for an Activity in Activity/Event/Cost Code 1, then select its check box.

- Enter the Allocated Hours for the person, ensuring they match the Working Hours, then select the correct Rate Code + Unit of Measure.
- Enter the Allocated Hours for any equipment as needed, ensuring they match the Working Hours,
then select a Rate Code + Unit of Measure. - Leave comments in Describe the work performed and Resource Comments as needed.
- To add additional Codes, click Yes on ‘Add another Activity/Event/Cost Code?’ as needed.
- Up to three (3) Activities can be selected.
- In Submitter, select the person submitting the Docket, then have them sign in the box.

- Click Clear to clear the signature box.
- In Select Reviewer, select the icon to choose who will approve the Docket.
- When all details are entered, select Submit.
Note: Information entered here will autofill in future entries; the same process can be followed for both Labour and Plant Dockets