Scheduling


Can I display multiple ‘Project Week’ bars from different calendars on the Timescale in the Gantt?

Is it possible to expand the number of characters allowed in Activity Codes?

Why can’t I navigate the Gantt Chart with a project with Tasks spanning upwards of 100yrs?

How can I generate report for a time-distributed Resource utilization?

When I export an animation, the focus time does not display ‘Week 1’ when the construction starts. Can I change the construction start week manually?

How can I turn of link lines in the Gantt chart?

How do we merge two separate SYNCHRO Pro SP files into one Master SP file?

Can I use SYNCHRO Scheduler to modify SYNCHRO Pro files?

After recording Actual Finish Date for a Task A and Rescheduling, why does its successor Task B, with FS relationship, moves to the start of the Task A instead of starting after Task A finished date?

How can I get an S-Curve from SYNCHRO Pro to Excel?

Why doesn't the Task progress finish line (blue fill) end at the Data Date line (vertical blue dotted line)?

Is there a way to modify the Resource Appearance Profile for multiple tasks?