Project Settings


Each project can be configured independently using the settings. The settings control the behaviour of the project including some reference data. Settings can be edited at any time.

Setting Area

Use

Possible values

Mandatory

General Settings

 

 

 

System Admin

 

 

 

Name

The name of the project

 

Status Type

Used for grouping projects according to status

· Active (default)

· Training

· Archive

Default cost unit of measure

Sets the UoM for Activity Revised Budget Values which are consistent across all Activities and are displayed on reports

Based on UoM configuration

Protected classification

To enable the Australian Government's Protective Security Policy Framework's 'Protected' classification for a project.

External reference

Unique identifier

 

 

Location

Short name or address describing the location of project

 

 

Location Latitude

Latitude represented as a decimal angle

(e.g., -27.463881) [-90 < latitude < 90]

 

Location Longitude

Longitude represented as a decimal angle

(e.g., 153.012451) [-180 < longitude < 180]

 

Project support contact

Project support contact details - shown in Help menu

Name, telephone number, email

 

Date format

Format of how dates are shown in the project

dd/mm/yyyy or mm/dd/yyyy

Tags

Tags created here act as placeholder tags and may be applied to other entities

 

 

Author copyable comment/attachment tags

Tags created here, and when present on a person, will be automatically applied to new comments and attachments that person creates

 

 

Person display name format

The default name format for people names across all pages within SYNCHRO Perform (case sensitive)

· Given Family (default)

· FAMILY, Given

· FAMILY, GIVEN

· FAMILY Given

· Family Given

· Attendance Ref (5 chars), FAMILY, GIVEN [Supervisor Code]

Classification period for Events

Number of hours in which a new Event must be classified

 

 

Editable discussion period for Comments

Number of hours for which Comments are editable

 

Record time of status change on work

Automatically record times for status changes on Activities and Events

 

                                                        

 

 

Tagged Item actual quantity resolution order

The first populated quantity will be used as the Actual Quantity at complete for Tagged Item Activities

· Actual Quantity at Complete (default)

· Actual Quantity at Complete > Revised Budget Quantity

· Actual Quantity at Complete > Current Budget Quantity

· Actual Quantity at Complete > Revised Budget Quantity > Current Budget Quantity

· Actual Quantity at Complete > Current Budget Quantity > Revised Budget Quantity

Default Usage Codes

 

 

 

For People

The default Usage Code that is applied to People Resource Usages (Usage Code is mandatory for all Usages)

Defaults to “Normal (N)”

For Equipment

The default Usage Code that is applied to Equipment Resource Usages (Usage Code is mandatory for all Usages)

Defaults to “Normal (N)”

For Other

The default Usage Code that is applied to Other Resource Usages (Usage Code is mandatory for all Usages)

Defaults to “Normal (N)”

Timesheet / Resource Usage configuration

 

 

Default timesheet entry day

 

· Today (default)

· Yesterday

Allow negative Resource Usage values

Allow resource usages to be entered with negative amounts

 

 

Allow self-approval of Resource Usages

Only affects Users below System Admin that are permitted to approve entries. Does not affect Client Resource Usage approvals. Only System Admins can change

 

 

Allow rejection of approved Resource Usages

Only affects Users below Project Config that are permitted to reject entries. Does not affect Client Resource Usage approvals. Only System Admins can change

 

 

Allow Standard Users to create and assign Resources

Allow standard Users to create and assign Resources via the Resource Usage Matrix

 

 

Allow Subcontractor Users to export Resource Usages

Allow subcontractor users to export Resource Usages

 

 

Relax Work Reference constraints on Bulk Create & SYNCHRO Perform Mobile

Relaxes supervisor and actual date constraints on Bulk Create & SYNCHRO Perform Mobile to match the Resource Usage Matrix

 

 

Relax work reference constraints on Resource Usage Entry & Resource Usage Matrix

Relaxes actual date and active work reference constraints on Resource Usage Entry & Resource Usage Matrix

 

 

Show start/end times on the Resource Usage Matrix, Resource Usage Entry, and Bulk Create pages

Enables Start Time, End Time, and Break Duration columns on the Resource Usage Matrix, Resource Usage Entry, and Bulk Create pages

 

 

Show SMU Start/End on the Resource Usage Entry and Bulk Create pages

Shows options to enter Start/End SMU (Service Meter Unit) amounts Equipment Resources on the Resource Usage Entry and Bulk Create pages

 

 

Show the First Receiver column on Bulk Create

Shows the First Receiver column on Bulk Create which will set the First Receiver of a Docket when provided

 

 

Automatically create Dockets for each resource with Usage

Automatically created dockets will have a docket reference in the format of "CPY-RES-YYYYMMDD"

 

 

Require Rate Code to be specified on Resource Usages

This only applies if a Rate exists for the specified resource and date

 

 

Require a Resource Assignment for Resources on Resource Usages

This will require the Resource specified on a Resource Usage to have a Resource Assignment which covers the specified work date

 

 

Require a Resource Assignment for Resources on Attendances

This will require the Resource specified on an Attendance to have a Resource Assignment which covers the specified work date

 

 

Enable cascading of approval and locking on Invoices, Dockets, and Resource Usages

Will approve and lock associated Dockets when an Invoice is Processed. Will approve and lock associated Resource Usages when a Docket is Approved.

Enabling this setting does not cascade approve historical data. If you would like to cascade approve historical data, please contact SYNCHRO Perform Support

 

 

Notice notifications

 

 

Default Notice notification email addresses

Email addresses entered here will be automatically applied to Notice notifications

Example: “john@example.com, jane@example.com” (comma separated list)

 

Daily Unissued Notices Summary notification email recipients

Email addresses entered here will automatically be sent a Daily Unissued Notices Summary email

Example: “john@example.com, jane@example.com” (comma separated list)

 

Docket notifications

 

 

Docket notification email

When a Docket changes state, send this email a notification

 

 

Send daily docket summary to each subcontractor

Send a daily notification email with a docket-state-change summary to all Subcontractor Companies containing only Dockets with at least one state change from the previous day and only with the last change if the docket's state was updated multiple times

 

 

On creation

 

 

 

Send docket create notification to creator

When a Docket is created via mobile, send a notification email to the Creator

 

 

Send docket create notification to first receiver

Send notification email to docket's first receiver on a newly created Docket

 

 

Send docket create notification to each person

Send notification emails to all People with a Resource Usage on a newly created Docket

 

 

Send docket create notification to subcontractor company

Send a notification email to the Subcontractor Company on a newly created Docket

 

 

On state change

When a Docket changes state, send notification emails to the Creator, the Docket's Subcontractor Company, the Project Docket notification email, and any additional recipients specified on the Docket

 

 

Send docket received notification

Send a notification when the status of the Docket changes to Received

 

 

Send docket approved notification

Send a notification when the status of the Docket changes to Approved

 

 

Send docket rejected notification

Send a notification when the status of the Docket changes to Rejected

 

 

On state change (to each person on Docket)

When a Docket changes state, send notification emails to all People with a Resource Usage on the Docket

 

 

Send docket received notification to each person

Send a notification when the status of the Docket changes to Received

 

 

Send docket approved notification to each person

Send a notification when the status of the Docket changes to Approved

 

 

Send docket rejected notification to each person

Send a notification when the status of the Docket changes to Rejected

 

 

SYNCHRO Perform Mobile

 

 

Apply default Rate Code to Resource Usages

If the Rate for a Resource is marked as “Default”, apply the corresponding Rate Code to the Resource Usage

 

 

Add a watermark displaying location, date and time to captured images

Watermark is automatically applied to all images capture or uploaded to SYNCHRO Perform via the mobile app

 

 

Make Tags a mandatory field on the Comment/Photo screen

Forces a Tag or Tags to be selected when using the Comment/Photo screen

 

 

Enable Quantity Progress entry on the Comment/Photo screen

Allows a Quantity Progress amount to be entered for Activities that have an Earned Value Method of “quantity” via the Comment/Photo screen

 

 

Make Attendance Area a mandatory field on all Attendance screens

Forces an Attendance Area to be selected when submitting an Attendance entry

 

 

Require GPS location on Start/End/Bulk Attendance screens

Forces GPS location to be captured for Attendance entries

Show Competencies for the scanned Person on the Start/End Attendance screens

Ensure a Person's  Competencies are shown when scanning a QR for Attendance

Show Rate Code and Unit of Measure selector on the Crew Timesheet/Docket screens

If there is an applicable Rate for a Resource, the Rate Code and Unit of Measure will be shown on the Timesheet/Docket screens

Additional Docket submission for the same resource

 

 

 

·        Add Resource Usages to existing Dockets (duplicate Resource Usages will be unprocessable)

The uniqueness constraint of Resource Usages is applied thereby making duplicate Resource Usages unprocessable

 

 

·        Create new Dockets with distinct Resource Usages (duplicate Resource Usages will be allowed)

The uniqueness constraint of Resources Usages is avoided thereby allowing duplicate Resource Usages

 

 

Default note for Attendance start

Used as the default note when creating an Attendance start on mobile

 

 

Default note for Attendance end

Used as the default note when creating an Attendance end on mobile

 

 

Activity/Event for Attendance timesheets

The Activity/Event used for timesheet entries on the Start/End/Bulk Attendance screens

 

Client Resource Usage Approvals

When a Resource Usage is Submitted to the Client for Approval or Approved/Rejected by the Client, send notifications to the specified email recipients

 

 

Allow Clients to approve Resource Usages

Allow Resource Usages to be submitted to the Client for approval or rejection

 

 

Submitted to Client notification email recipients

Send a notification to the email address(es) when the Resource Usage is Submitted for Client Approval to the Client Resource Usage Approver user

Example: “john@example.com, jane@example.com” (comma separated list)

 

Rejected by Client notification email recipients

Send a notification to the email address(es) when the Resource Usage is Rejected by the Client Resource Usage Approver user

Example: “john@example.com, jane@example.com” (comma separated list)

 

Approved by Client notification email recipients

Send a notification to the email address(es) when the Resource Usage is Approved by the Client Resource Usage Approver user

Example: “john@example.com, jane@example.com” (comma separated list)

 

Internal Resource Usage Approvals

When a Resource Usage is Submitted/Approved/Rejected internally, send notifications to the specified email recipients

 

 

Submitted notification email recipients

Send a notification to the email address(es) when the Resource Usage is Submitted

Example: “john@example.com, jane@example.com” (comma separated list)

 

Rejected notification email recipients

Send a notification to the email address(es) when the Resource Usage is Approved

Example: “john@example.com, jane@example.com” (comma separated list)

 

Approved notification email recipients

Send a notification to the email address(es) when the Resource Usage is Rejected

Example: “john@example.com, jane@example.com” (comma separated list)

 

Reporting periods

 

 

 

Weekly period ending day

The day of the week on which the weekly period ends on the Resource Usage Summary page

Default: Sunday

Monthly period ending day

The date or day of the month on which the monthly period ends in Analytics

Use “31” for the last day of the month

 

Reporting parameters

 

 

 

Custom project Report values

Values defined here can be included in Report and Notice Templates

Example: client_name=Important Customer Pty Ltd

 

Import column mappings

 

 

 

Import column mappings

Column headers from external systems can be mapped to SYNCHRO Perform column headers on imports

Example: Custom Name=system_name

 

Report Logo

Upload report logo

Upload a company logo for use in templated reports.jpeg or.png format