Product(s): | Exor Noticing Manager | ||
Version(s): | 4.7.0.0 | ||
Environment: | N/A | ||
Area: | Other | ||
Subarea: | N/A |
The earliest start date for Major notices displayed in system are starting ahead of our jobs to commence date. The User had raised notice on 28th February and needed the job to commence on the 28th May, but the system showed the earliest start date as 31st May.
The issue here is you have to give 3 full months notice. If a notice is raised on last day of the calendar month, then the earliest start date would be on the last day of the month in 3 months.
February month is an exception as it has only 28 days, in this case the earliest date is the end of May.
Bentley Technical Support KnowledgeBase
Original Author: | Jyoti Patil |